ONSHORE WIND Β· MISO

Onshore wind project G275, Mcpherson County

Onshore wind project G275, Mcpherson County is a 19.0 MW onshore wind request withdrawn in the MISO interconnection queue, in Mcpherson County, South Dakota.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Dec 2002 (completed)
  2. Withdrawn / abandonedApr 2003 (project stopped here)
  3. ConsentedApr 2003 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
G275
Grid region
MISO (Midcontinent)
Connection point (POI)
Unknown
Location
Mcpherson County, South Dakota
Technology
Wind: 19.0 MW
Total requested
19.0 MW
Queue status
Withdrawn
Entered queue
12 December 2002
Agreement signed
17 April 2003
Proposed online date
September 2004
Withdrawn
April 2003

Location

Marker shows the centre of Mcpherson County; the queue data does not give exact sites.

Power plants in South Dakota Β· Transmission lines in South Dakota

Other requests in Mcpherson County