πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί New York

ONSHORE WIND Β· NYISO

Black Oak Wind

Black Oak Wind is a 12.5 MW onshore wind request withdrawn in the NYISO interconnection queue, in Tompkins County, New York, connecting to NYSEG.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jan 2013 (completed)
  2. Withdrawn / abandonedAug 2017 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
398
Grid region
NYISO (New York)
Utility / transmission owner
NYSEG
Developer
Black Oak Wind Farm, LLC
Connection point (POI)
Montour - Coddington 115kV
Location
Tompkins County, New York
Technology
Wind: 12.5 MW
Total requested
12.5 MW
Queue status
Withdrawn
Entered queue
10 January 2013
Withdrawn
August 2017

Location

Marker shows the centre of Tompkins County; the queue data does not give exact sites.

Power plants in New York Β· Transmission lines in New York

Other requests in Tompkins County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem