SOLAR Β· PJM

Solar project AG2-036, Gloucester County

Solar project AG2-036, Gloucester County is a 10.0 MW solar request withdrawn in the PJM interconnection queue, in Gloucester County, New Jersey, connecting to AEC.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Nov 2020 (completed)
  2. Withdrawn / abandonedDec 2024 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
AG2-036
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
AEC
Connection point (POI)
Mantua 12 kV
Location
Gloucester County, New Jersey
Technology
Solar: 10.0 MW
Total requested
10.0 MW
Service type
Network resource (NRIS)
Study phase
Feasibility Study
Queue status
Withdrawn
Entered queue
13 November 2020
Proposed online date
December 2021
Withdrawn
December 2024

Location

Marker shows the centre of Gloucester County; the queue data does not give exact sites.

Power plants in New Jersey Β· Transmission lines in New Jersey

Other requests in Gloucester County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem