United States › Grid › Interconnection queues › New York

BATTERY STORAGE · NYISO

Far Rockaway Power Station Battery Energy Storage System (BESS)

Far Rockaway Power Station Battery Energy Storage System (BESS) is a 30.0 MW battery storage request withdrawn in the NYISO interconnection queue, in Queens County, New York, connecting to LIPA.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Nov 2019 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
939
Grid region
NYISO (New York)
Utility / transmission owner
LIPA
Developer
National Grid Generation LLC
Connection point (POI)
Far Rockaway 69kV
Location
Queens County, New York
Technology
Battery: 30.0 MW
Total requested
30.0 MW
Queue status
Withdrawn
Entered queue
5 November 2019

Location

Marker shows the centre of Queens County; the queue data does not give exact sites.

Power plants in New York · Transmission lines in New York

Other requests in Queens County