πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Connecticut

SOLAR Β· ISO-NE

Solar

Solar is a 22.0 MW solar request withdrawn in the ISO-NE interconnection queue, in New London County, Connecticut.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jul 2017 (completed)
  2. Withdrawn / abandonedSep 2017 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
675
Grid region
ISO-NE (New England)
Connection point (POI)
Eversource Bean Hill - Tunnel 115 kV
Location
New London County, Connecticut
Technology
Solar: 22.0 MW
Total requested
22.0 MW
Service type
Network resource (NRIS)
Queue status
Withdrawn
Entered queue
28 July 2017
Proposed online date
December 2019
Withdrawn
September 2017

Location

No county location in the queue data.

Power plants in Connecticut Β· Transmission lines in Connecticut

Other requests in New London County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem