Solar project G0584, Klickitat County

Solar project G0584, Klickitat County is a 100 MW solar request withdrawn in the West interconnection queue, in Klickitat County, Washington.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2018 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
G0584
Grid region
West (non-ISO utilities)
Connection point (POI)
Horse Heaven - Harvalum 230 kV line
Location
Klickitat County, Washington
Technology
Solar: 100 MW
Total requested
100 MW
Service type
NRIS and ERIS
Queue status
Withdrawn
Entered queue
19 March 2018
Proposed online date
July 2021

Location

Marker shows the centre of Klickitat County; the queue data does not give exact sites.

Power plants in Washington Β· Transmission lines in Washington

Other requests in Klickitat County