BATTERY STORAGE Β· ERCOTJack Barton BESS
Jack Barton BESS is a 47.3 MW battery storage request withdrawn in the ERCOT interconnection queue, in Jack County, Texas.
Queue statusWithdrawn / abandoned
- PlanningQueued Aug 2022 (completed)
- Withdrawn / abandonedDec 2025 (project stopped here)
- ConsentedMar 2024 (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 24INR0304
- Grid region
- ERCOT (Texas)
- Developer
- Jack Barton BESS
- Connection point (POI)
- 1599 Barton Chapel Wind Farm station 138kV
- Location
- Jack County, Texas
- Technology
- Battery: 47.3 MW
- Total requested
- 47.3 MW
- Study phase
- IA
- Queue status
- Withdrawn
- Entered queue
- 4 August 2022
- Agreement signed
- 17 March 2024
- Proposed online date
- April 2027
- Withdrawn
- December 2025
Location
Marker shows the centre of Jack County; the queue data does not give exact sites.
Other requests in Jack County
- Pinnington SolarSolar + storage Β· 654 MW Β· agreement signed
- O'Bannion Energy StorageBattery storage Β· 306 MW Β· agreement signed
- Fortuna WindOnshore wind Β· 295 MW Β· agreement signed
- Dovetail Solar 3Solar + storage Β· 666 MW Β· in study
- Dovetail Solar 1Solar + storage Β· 666 MW Β· in study
- Dovetail Solar 2Solar + storage Β· 666 MW Β· in study
- Jack County III βΓΓ¬ 345 kVGas Β· 660 MW Β· in study
- Dovetail StorageSolar + storage Β· 509 MW Β· in study
- Pinnington StorageSolar + storage Β· 503 MW Β· in study
- Wooderson Energy StorageBattery storage Β· 306 MW Β· in study
- Possum Kingdom SolarSolar + storage Β· 262 MW Β· in study
- Campsey WindOnshore wind Β· 238 MW Β· in study