BATTERY STORAGE Β· ERCOT

Jack Barton BESS

Jack Barton BESS is a 47.3 MW battery storage request withdrawn in the ERCOT interconnection queue, in Jack County, Texas.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Aug 2022 (completed)
  2. Withdrawn / abandonedDec 2025 (project stopped here)
  3. ConsentedMar 2024 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
24INR0304
Grid region
ERCOT (Texas)
Developer
Jack Barton BESS
Connection point (POI)
1599 Barton Chapel Wind Farm station 138kV
Location
Jack County, Texas
Technology
Battery: 47.3 MW
Total requested
47.3 MW
Study phase
IA
Queue status
Withdrawn
Entered queue
4 August 2022
Agreement signed
17 March 2024
Proposed online date
April 2027
Withdrawn
December 2025

Location

Marker shows the centre of Jack County; the queue data does not give exact sites.

Power plants in Texas Β· Transmission lines in Texas

Other requests in Jack County