SOLAR + STORAGE · ERCOT

White Wing Solar

White Wing Solar is a 127 MW solar + storage request in interconnection study in the ERCOT interconnection queue, in Wilbarger County, Texas.

Queue statusIn planning
  1. PlanningQueued Aug 2025 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Jul 2028 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
27INR0332
Grid region
ERCOT (Texas)
Developer
White Wing Solar, LLC
Connection point (POI)
Tap 345 kV (#60504) Tesla - (#6111) Riley
Location
Wilbarger County, Texas
Technology
Solar: 127 MW · Battery
Total requested
127 MW
Study phase
SS Completed, FIS Started, No IA
Queue status
Active
Entered queue
13 August 2025
Proposed online date
July 2028

Location

Marker shows the centre of Wilbarger County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Wilbarger County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem