Solar + storage project 25-00420, Clark County

Solar + storage project 25-00420, Clark County is a 500 MW solar + storage request in interconnection study in the West interconnection queue, in Clark County, Nevada, connecting to NV Energy.

Queue statusIn planning
  1. PlanningQueued Jul 2025 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Sep 2029 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
25-00420
Grid region
West (non-ISO utilities)
Utility / transmission owner
NV Energy
Location
Clark County, Nevada
Technology
Solar: 500 MW · Battery
Total requested
500 MW
Service type
NRIS and ERIS
Study phase
In Progress (unknown study)
Queue status
Active
Entered queue
30 July 2025
Proposed online date
September 2029

Location

Marker shows the centre of Clark County; the queue data does not give exact sites.

Power plants in Nevada · Transmission lines in Nevada

Other requests in Clark County