πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Pennsylvania

SOLAR Β· PJM

Solar project AH2-108, Lawrence County

Solar project AH2-108, Lawrence County is a 35.0 MW solar request withdrawn in the PJM interconnection queue, in Lawrence County, Pennsylvania, connecting to ATSI.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Feb 2022 (completed)
  2. Withdrawn / abandonedMar 2022 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
AH2-108
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
ATSI
Connection point (POI)
Potter-Harlan 69 kV
Location
Lawrence County, Pennsylvania
Technology
Solar: 35.0 MW
Total requested
35.0 MW
Service type
Network resource (NRIS)
Study phase
Feasibility Study
Queue status
Withdrawn
Entered queue
11 February 2022
Proposed online date
June 2026
Withdrawn
March 2022

Location

Marker shows the centre of Lawrence County; the queue data does not give exact sites.

Power plants in Pennsylvania Β· Transmission lines in Pennsylvania

Other requests in Lawrence County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem