Solar project J3285, Vigo County

Solar project J3285, Vigo County is a 150 MW solar request withdrawn in the MISO interconnection queue, in Vigo County, Indiana, connecting to DUKE ENERGY INDIANA.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2024 (completed)
  2. Withdrawn / abandonedAug 2024 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J3285
Grid region
MISO (Midcontinent)
Utility / transmission owner
DUKE ENERGY INDIANA
Connection point (POI)
TH Pfizer Jct. - Worthington (HED)
Location
Vigo County, Indiana
Technology
Solar: 150 MW
Total requested
150 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: DPP 1
Queue status
Withdrawn
Entered queue
15 April 2024
Proposed online date
September 2028
Withdrawn
August 2024

Location

Marker shows the centre of Vigo County; the queue data does not give exact sites.