United States β€Ί Grid β€Ί Interconnection queues β€Ί Utah

SOLAR Β· WEST

Solar project 820, Beaver County

Solar project 820, Beaver County is a 48.0 MW solar request withdrawn in the West interconnection queue, in Beaver County, Utah, connecting to PacifiCorp.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Nov 2016 (completed)
  2. Withdrawn / abandonedSep 2022 (project stopped here)
  3. ConsentedNov 2019 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
820
Grid region
West (non-ISO utilities)
Utility / transmission owner
PacifiCorp
Developer
Grass Butte Solar, LLC
Connection point (POI)
South Milford substation
Location
Beaver County, Utah
Technology
Solar: 48.0 MW
Total requested
48.0 MW
Service type
Energy only (ERIS)
Study phase
IA Executed 11/7/19, Suspended 3/20/2020, IA terminated 9/2/2022
Queue status
Withdrawn
Entered queue
15 November 2016
Agreement signed
7 November 2019
Proposed online date
February 2018
Withdrawn
September 2022

Location

Marker shows the centre of Beaver County; the queue data does not give exact sites.

Power plants in Utah Β· Transmission lines in Utah

Other requests in Beaver County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem