Webster BESS

Webster BESS is a 8.8 MW battery storage request withdrawn in the NYISO interconnection queue, in Monroe County, New York, connecting to RG&E.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Nov 2019 (completed)
  2. Withdrawn / abandonedMay 2020 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
948
Grid region
NYISO (New York)
Utility / transmission owner
RG&E
Developer
Dimension NY 1 LLC
Connection point (POI)
34.5 kV
Location
Monroe County, New York
Technology
Battery: 8.8 MW
Total requested
8.8 MW
Queue status
Withdrawn
Entered queue
18 November 2019
Withdrawn
May 2020

Location

Marker shows the centre of Monroe County; the queue data does not give exact sites.