ONSHORE WIND Β· WEST

Onshore wind project 12, Garfield County

Onshore wind project 12, Garfield County is a 200 MW onshore wind request withdrawn in the West interconnection queue, in Garfield County, Washington, connecting to Avista Utilities.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jan 2008 (completed)
  2. Withdrawn / abandonedOct 2010 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
12
Grid region
West (non-ISO utilities)
Utility / transmission owner
Avista Utilities
Connection point (POI)
Dry Creek-Talbot 230 kV
Location
Garfield County, Washington
Technology
Wind: 200 MW
Total requested
200 MW
Service type
NRIS and ERIS
Queue status
Withdrawn
Entered queue
9 January 2008
Proposed online date
December 2011
Withdrawn
October 2010

Location

Marker shows the centre of Garfield County; the queue data does not give exact sites.

Power plants in Washington Β· Transmission lines in Washington

Other requests in Garfield County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem