COAL Β· PJMNorth Haverhill
North Haverhill is a 75.0 MW coal request built and operating in the PJM interconnection queue, in Scioto County, Ohio, connecting to AEP.
Request details
- Queue ID
- N12
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- AEP
- Connection point (POI)
- North Haverhill 69 kV
- Location
- Scioto County, Ohio
- Technology
- Coal: 75.0 MW
- Total requested
- 75.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- Available studies: Feasibility Study, System Impact Study, Facilities Study; Interim/Interconnection Service Agreement:
- Queue status
- Operational
- Entered queue
- 13 October 2004
- Agreement signed
- 28 February 2007
- Proposed online date
- June 2009
- Came online
- June 2009
Location
Marker shows the centre of Scioto County; the queue data does not give exact sites.
Other requests in Scioto County
- Coal project X1-027, Scioto CountyCoal Β· 200 MW Β· withdrawn
- Coal project T152, Scioto CountyCoal Β· 140 MW Β· withdrawn
- Solar project AC2-026, Scioto CountySolar Β· 50.0 MW Β· withdrawn
- Solar project AD1-141, Scioto CountySolar Β· 50.0 MW Β· withdrawn
- Coal project AD2-078, Scioto CountyCoal Β· 40.0 MW Β· withdrawn
- Solar project AC2-047, Scioto CountySolar Β· 18.3 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem