πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Utah

SOLAR + STORAGE Β· WEST

Solar + storage project T2-091, Iron County

Solar + storage project T2-091, Iron County is a 400 MW solar + storage request withdrawn in the West interconnection queue, in Iron County, Utah, connecting to PacifiCorp.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Sep 2025 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
T2-091
Grid region
West (non-ISO utilities)
Utility / transmission owner
PacifiCorp
Connection point (POI)
Three Peaks substation
Location
Iron County, Utah
Technology
Solar: 400 MW Β· Battery
Total requested
400 MW
Service type
Energy only (ERIS)
Queue status
Withdrawn
Entered queue
12 September 2025
Proposed online date
May 2027

Location

Marker shows the centre of Iron County; the queue data does not give exact sites.

Power plants in Utah Β· Transmission lines in Utah

Other requests in Iron County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem