Bethlehem Battery

Bethlehem Battery is a 10.0 MW battery storage request withdrawn in the NYISO interconnection queue, in Albany County, New York, connecting to NM-NG.

Queue statusWithdrawn / abandoned
  1. PlanningQueued May 2018 (completed)
  2. Withdrawn / abandonedNov 2018 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
707
Grid region
NYISO (New York)
Utility / transmission owner
NM-NG
Developer
PSEG Power NY LLC
Connection point (POI)
Albany Substation 115kV
Location
Albany County, New York
Technology
Battery: 10.0 MW
Total requested
10.0 MW
Queue status
Withdrawn
Entered queue
4 May 2018
Withdrawn
November 2018

Location

Marker shows the centre of Albany County; the queue data does not give exact sites.

Power plants in New York · Transmission lines in New York

Other requests in Albany County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem