SOLAR Β· ERCOT

McGee Solar

McGee Solar is a 153 MW solar request withdrawn in the ERCOT interconnection queue, in Henderson County, Texas.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Nov 2022 (completed)
  2. Withdrawn / abandonedMay 2024 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
24INR0470
Grid region
ERCOT (Texas)
Developer
BT McGee Solar, LLC
Connection point (POI)
Bus #6843 at Rayburn Barton Chapel Substation
Location
Henderson County, Texas
Technology
Solar: 153 MW
Total requested
153 MW
Study phase
FIS
Queue status
Withdrawn
Entered queue
14 November 2022
Proposed online date
December 2024
Withdrawn
May 2024

Location

Marker shows the centre of Henderson County; the queue data does not give exact sites.

Power plants in Texas Β· Transmission lines in Texas

Other requests in Henderson County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem