United States βΊ Grid βΊ Interconnection queues βΊ Texas
SOLAR Β· ERCOTOld Jackson Solar
Old Jackson Solar is a 129 MW solar request withdrawn in the ERCOT interconnection queue, in Van Zandt County, Texas.
Queue statusWithdrawn / abandoned
- PlanningQueued Sep 2017 (completed)
- Withdrawn / abandonedNov 2020 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 19INR0123
- Grid region
- ERCOT (Texas)
- Developer
- OLD JACKSON SOLAR LLC
- Connection point (POI)
- tap 138kV 3175 Canton - 3173 Expmtr
- Location
- Van Zandt County, Texas
- Technology
- Solar: 129 MW
- Total requested
- 129 MW
- Study phase
- FIS
- Queue status
- Withdrawn
- Entered queue
- 11 September 2017
- Proposed online date
- April 2021
- Withdrawn
- November 2020
Location
Marker shows the centre of Van Zandt County; the queue data does not give exact sites.
Other requests in Van Zandt County
- Zorro BESSBattery storage Β· 154 MW Β· agreement signed
- Whiskey BESSBattery storage Β· 154 MW Β· agreement signed
- Caney Creek SolarSolar Β· 121 MW Β· agreement signed
- Amador StorageBattery storage Β· 102 MW Β· agreement signed
- Sierra Diablo Energy StorageBattery storage Β· 204 MW Β· in study
- Wood Fern WindOnshore wind Β· 197 MW Β· in study
- Goldfinch SolarSolar + storage Β· 151 MW Β· in study
- Benitoite StorageBattery storage Β· 126 MW Β· in study
- Edgewood BESS 2Battery storage Β· 102 MW Β· in study
- Edgewood BESS 1Battery storage Β· 102 MW Β· in study
- Goldfinch StorageSolar + storage Β· 100 MW Β· in study
- Kellam SolarSolar Β· 59.8 MW Β· built
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem