Knickerbocker Storage II

Knickerbocker Storage II is a 178 MW other request withdrawn in the ERCOT interconnection queue, in Tom Green County, Texas.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Feb 2022 (completed)
  2. Withdrawn / abandonedMar 2022 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
25INR0043
Grid region
ERCOT (Texas)
Developer
San Angelo Solar 2 LLC
Connection point (POI)
Tap 345kV 76003 Big Hill - 76009 Twin Buttes_x000D_
Location
Tom Green County, Texas
Technology
Other: 178 MW
Total requested
178 MW
Study phase
FIS & SS Incomplete
Queue status
Withdrawn
Entered queue
20 February 2022
Proposed online date
January 2025
Withdrawn
March 2022

Location

Marker shows the centre of Tom Green County; the queue data does not give exact sites.