United States › Grid › Interconnection queues › Texas
OTHER · ERCOTRegis Palacios BESS
Regis Palacios BESS is a 9.9 MW other request built and operating in the ERCOT interconnection queue, in Matagorda County, Texas.
Request details
- Queue ID
- 22INR0602
- Grid region
- ERCOT (Texas)
- Developer
- Regis Palacios, LLC
- Connection point (POI)
- Station Name (TSP STATION CODE): Palacios_x000D_ Load Name or Load Transformer name: 69_12_2_x000D_ Bus# PTI Bus number: 8131_x000D_ Voltage Transmission level kV: 69kV
- Location
- Matagorda County, Texas
- Technology
- Other: 9.9 MW
- Total requested
- 9.9 MW
- Study phase
- MRD Approved
- Queue status
- Operational
- Entered queue
- 7 April 2023
- Proposed online date
- November 2024
- Came online
- November 2024
Location
Marker shows the centre of Matagorda County; the queue data does not give exact sites.
Other requests in Matagorda County
- Duffy SolarSolar + storage · 503 MW · agreement signed
- Lavaca Bay SolarSolar · 244 MW · agreement signed
- Peyton Creek Wind IIOnshore wind · 241 MW · agreement signed
- Duffy BESSSolar + storage · 241 MW · agreement signed
- Eldora BESSSolar + storage · 201 MW · agreement signed
- Eldora SolarSolar + storage · 201 MW · agreement signed
- City Breeze BESSBattery storage · 143 MW · agreement signed
- Matagorda SolarSolar · 101 MW · agreement signed
- Isaac SolarSolar · 50.7 MW · agreement signed
- Bluefox Solar 1Solar · 403 MW · in study
- Bluefox Solar 2Solar · 402 MW · in study
- Juanita Creek BESSBattery storage · 304 MW · in study
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem