Solar + storage project IC-1090, Lowndes County

Solar + storage project IC-1090, Lowndes County is a 40.0 MW solar + storage request withdrawn in the Southeast interconnection queue, in Lowndes County, Alabama, connecting to Southern Company.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Nov 2022 (completed)
  2. Withdrawn / abandonedMar 2023 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
IC-1090
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Southern Company
Connection point (POI)
Lowndesboro DS Substation 46 kV Bus
Location
Lowndes County, Alabama
Technology
Solar: 40.0 MW Β· Battery
Total requested
40.0 MW
Service type
NRIS and ERIS
Study phase
Withdrawn
Queue status
Withdrawn
Entered queue
15 November 2022
Withdrawn
March 2023

Location

Marker shows the centre of Lowndes County; the queue data does not give exact sites.