πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Texas

ONSHORE WIND Β· ERCOT

Rattlesnake Wind

Rattlesnake Wind is a 205 MW onshore wind request withdrawn in the ERCOT interconnection queue, in Hardeman County, Texas.

Queue statusWithdrawn / abandoned
  1. Planning (completed)
  2. Withdrawn / abandonedMar 2023 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
25INR0127
Grid region
ERCOT (Texas)
Developer
Rattlesnake Wind
Connection point (POI)
Riley to Tesla 345 kV line tap
Location
Hardeman County, Texas
Technology
Wind: 205 MW
Total requested
205 MW
Study phase
FIS & SS Incomplete
Queue status
Withdrawn
Proposed online date
August 2025
Withdrawn
March 2023

Location

Marker shows the centre of Hardeman County; the queue data does not give exact sites.

Power plants in Texas Β· Transmission lines in Texas

Other requests in Hardeman County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem