πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Nevada

SOLAR Β· WEST

Solar project Company HI, Nye County

Solar project Company HI, Nye County is a 100 MW solar request withdrawn in the West interconnection queue, in Nye County, Nevada, connecting to NV Energy.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Sep 2016 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
Company HI
Grid region
West (non-ISO utilities)
Utility / transmission owner
NV Energy
Location
Nye County, Nevada
Technology
Solar: 100 MW
Total requested
100 MW
Service type
Network resource (NRIS)
Queue status
Withdrawn
Entered queue
22 September 2016
Proposed online date
September 2018

Location

Marker shows the centre of Nye County; the queue data does not give exact sites.

Power plants in Nevada Β· Transmission lines in Nevada

Other requests in Nye County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem