Solar + storage project Company 172, Clark County

Solar + storage project Company 172, Clark County is a 250 MW solar + storage request built and operating in the West interconnection queue, in Clark County, Nevada, connecting to NV Energy.

Queue statusOperating
  1. PlanningQueued Nov 2018 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingTarget Nov 2023 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
Company 172
Grid region
West (non-ISO utilities)
Utility / transmission owner
NV Energy
Location
Clark County, Nevada
Technology
Solar: 250 MW · Battery
Total requested
250 MW
Service type
NRIS and ERIS
Study phase
IA Executed
Queue status
Operational
Entered queue
30 November 2018
Proposed online date
November 2023

Location

Marker shows the centre of Clark County; the queue data does not give exact sites.

Power plants in Nevada · Transmission lines in Nevada

Other requests in Clark County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem