United States βΊ Grid βΊ Interconnection queues βΊ New Jersey
SOLAR Β· PJMGlassboro LF Solar
Glassboro LF Solar is a 2.0 MW solar request withdrawn in the PJM interconnection queue, in Gloucester County, New Jersey, connecting to AEC.
Queue statusWithdrawn / abandoned
- PlanningQueued Sep 2018 (completed)
- Withdrawn / abandonedApr 2025 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- AE1-218
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- AEC
- Connection point (POI)
- Glassboro 12 kV
- Location
- Gloucester County, New Jersey
- Technology
- Solar: 2.0 MW
- Total requested
- 2.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- Available studies: Feasibility Study, System Impact Study; Interim/Interconnection Service Agreement: Wholesale Market P
- Queue status
- Withdrawn
- Entered queue
- 28 September 2018
- Proposed online date
- July 2024
- Withdrawn
- April 2025
Location
Marker shows the centre of Gloucester County; the queue data does not give exact sites.
Power plants in New Jersey Β· Transmission lines in New Jersey
Other requests in Gloucester County
- Esky Solar ProjectSolar Β· 10.0 MW Β· agreement signed
- National Park NJSolar Β· 6.0 MW Β· agreement signed
- Monroe-Sicklerville Road LF SolarSolar Β· 1.6 MW Β· agreement signed
- Battery storage project AH2-378A, Gloucester CountyBattery storage Β· 200 MW Β· in study
- Battery storage project AH2-131, Gloucester CountyBattery storage Β· 104 MW Β· in study
- West Deptford Energy StationGas Β· 650 MW Β· built
- West Deptford Energy StationGas Β· 210 MW Β· built
- Eagle PointGas Β· 63.0 MW Β· built
- Eagle PointGas Β· 22.9 MW Β· built
- Gas project T59, Gloucester CountyGas Β· 14.4 MW Β· built
- West Deptford Energy StationGas Β· 9.0 MW Β· built
- Paradise SPSolar Β· 5.1 MW Β· built
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem