SOLAR · WEST

Solar project 472, Iron County

Solar project 472, Iron County is a 3.0 MW solar request built and operating in the West interconnection queue, in Iron County, Utah, connecting to PacifiCorp.

Queue statusOperating
  1. PlanningQueued Feb 2013 (completed)
  2. ConsentedJul 2015 (completed)
  3. Construction (completed)
  4. OperatingTarget Dec 2016 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
472
Grid region
West (non-ISO utilities)
Utility / transmission owner
PacifiCorp
Developer
Quichapa 2, LLC
Connection point (POI)
Circuit WCD28 out of West Cedar substation
Location
Iron County, Utah
Technology
Solar: 3.0 MW
Total requested
3.0 MW
Service type
Network resource (NRIS)
Study phase
IA Signed July 15, 2015
Queue status
Operational
Entered queue
28 February 2013
Agreement signed
15 July 2015
Proposed online date
December 2016

Location

Marker shows the centre of Iron County; the queue data does not give exact sites.