United States β€Ί Grid β€Ί Interconnection queues

OCTARY USA Β· INTERCONNECTION QUEUES

Hydro interconnection queue in the USA (2024 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown9222 MW
Active in queue222 MW9 requests
Agreement signed0.0 MW0 requests
Withdrawn4202 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

9 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Hydro project 957349, Oconee County
Hydro
112 MWIn study Oconee, SCSoutheast Jun 2024
Hydro project 648, Grainger County
Hydro
32.0 MWIn study Grainger, TNSoutheast Sep 2024target 2028
Hydro project 655, Hamilton County
Hydro
24.0 MWIn study Hamilton, TNSoutheast Sep 2024target 2028
Hydro project 654, Hamilton County
Hydro
24.0 MWIn study Hamilton, TNSoutheast Sep 2024target 2028
Hydro project 458, Broadwater County
Hydro
10.4 MWIn study Broadwater, MTWest Apr 2024
Hydro project 957051, Jackson County
Hydro
9.9 MWIn study Jackson, NCSoutheast Jun 2024
Hydro project 659, Loudon County
Hydro
4.0 MWIn study Loudon, TNSoutheast Oct 2024target 2028
Hydro project 658, Loudon County
Hydro
3.0 MWIn study Loudon, TNSoutheast Oct 2024target 2028
Hydro project 457, Lewis And Clark County
Hydro
2.2 MWIn study Lewis And Clark, MTWest Mar 2024target 2025

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)