Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Gas project 489, Roane County Gas |
1,689 MW | In study |
| Gas project 483, Stewart County Gas |
1,600 MW | In study |
| Texpo Gas Β· Oklaunion Power Station, LLC |
680 MW | In study |
| Bull Creek (Osceola Generating Station) Gas |
555 MW | Agreement signed |
| Elmax Power Station Gas Β· Elmax Generating, LLC |
519 MW | Agreement signed |
| Calpine Guadalupe Peakers Gas Β· Guadalupe Peaking Energy Center, LLC |
450 MW | In study |
| Gas project Q76, Pinal County Gas |
332 MW | In study |
| Gas project 113, Lewis County Gas |
219 MW | Paused / redesign |
| Gas project 114, Kitsap County Gas |
215 MW | Paused / redesign |
| Gas project J1834, Orange County Gas |
126 MW | In study |
| Gas project J1833, Lafourche Parish County Gas |
115 MW | Agreement signed |
| Gas project GI-2021-2, Weld County Gas |
49.0 MW | Agreement signed |
| Gas project GI-2021-3, Weld County Gas |
35.0 MW | Agreement signed |
| Gas project Q81, Maricopa County Gas |
30.0 MW | In study |
| Enchanted Rock NEWPP Gas Β· Generate ER-NG, LLC |
30.0 MW | Agreement signed |
| Midlothian 4 repower Gas Β· MIDLOTHIAN ENERGY, LLC |
18.0 MW | In study |
| Midlothian Unit 2 repower Gas Β· MIDLOTHIAN ENERGY, LLC |
18.0 MW | In study |
| Midlothian Unit 3 repower Gas Β· MIDLOTHIAN ENERGY, LLC |
18.0 MW | In study |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
- Southeast (non-ISO utilities)3 Β· 3,844 MW
- ERCOT (Texas)7 Β· 1,733 MW
- West (non-ISO utilities)6 Β· 880 MW
- MISO (Midcontinent)2 Β· 241 MW
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)