πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues

OCTARY USA Β· INTERCONNECTION QUEUES

Gas interconnection queue in the USA (2019 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown153,026 MW
Active in queue3,026 MW15 requests
Agreement signed2,091 MW10 requests
Withdrawn5823.5 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

15 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Gas project J1246, Iberville Parish County
Gas
725 MWAgreement signed Iberville Parish, LAMISO Apr 2019target 2025
Gas project 401, Humphreys County
Gas
593 MWAgreement signed Humphreys, TNSoutheast Sep 2019target 2023
Chesterfield CT Units 3&4
Gas
569 MWAgreement signed Chesterfield, VAPJM Sep 2019target 2029
Chesterfield CT Units 1 and 2
Gas Β· Virginia Electric and Power Company (d/b/a Dominion Energy Virginia)
569 MWIn study Chesterfield, VAPJM Sep 2019target 2029
Greens Bayou Expansion
Gas
140 MWPaused / redesign Harris, TXERCOT Apr 2019
Replace 103.1 MW of Heskett Units 1 & 2 with One (1) General Electric synchronous combustion turbine; Heskett 1 & 2
Gas
103 MWIn study Morton, NDMISO Jun 20192024
Gas project J1359, Linn County
Gas
95.0 MWIn study Linn, IAMISO Apr 2019target 2025
Gas project GI-78, Mayes County
Gas
52.0 MWAgreement signed Mayes, OKSoutheast Jan 2019target 2020
Gas project GI-77, Mayes County
Gas
50.0 MWAgreement signed Mayes, OKSoutheast Jan 2019target 2019
West Lorain Power Plant 345 kV
Gas
33.0 MWAgreement signed Lorain, OHPJM Oct 2019target 2031
Gas project G0620, Umatilla County
Gas
27.0 MWIn study Umatilla, ORWest Apr 2019target 2019
Gas project J1262, Wayne County
Gas
25.0 MWAgreement signed Wayne, MIMISO Apr 2019target 2022
Wise County Power Repower (CT1, CT2)
Gas Β· Wise County Power Company LLC
21.0 MWAgreement signed Wise, TXERCOT Jul 2019target 2026
Gas project GEN-2019-019, Woodbury County
Gas
15.2 MWAgreement signed Woodbury, IASPP Apr 20192022
West Lorain 138 kV Power Plant
Gas
8.0 MWAgreement signed Lorain, OHPJM Oct 2019target 2028

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)