United States β€Ί Grid β€Ί Interconnection queues β€Ί Wisconsin

OCTARY USA Β· INTERCONNECTION QUEUES

Interconnection queue in Wisconsin (2020 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown162,521 MW
Active in queue2,521 MW16 requests
Agreement signed1,921 MW13 requests
Withdrawn192,348 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

16 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Onshore wind project J1781, Iowa County
Onshore wind
300 MWUnder construction Iowa, WIMISO Jun 2020target 2027
Onshore wind project J1773, Lafayette County
Onshore wind
300 MWAgreement signed Lafayette, WIMISO Jun 2020target 2027
Solar project J1573, Portage County
Solar
250 MWAgreement signed Portage, WIMISO Jun 2020target 2026
Solar project J1502, Juneau County
Solar
225 MWAgreement signed Juneau, WIMISO Jun 2020target 2026
Solar project J1808, Barron County
Solar
200 MWIn study Barron, WIMISO Jun 2020target 2026
Solar project J1629, Columbia County
Solar
200 MWAgreement signed Columbia, WIMISO Jun 2020target 2027
Solar project J1615, Oconto County
Solar
150 MWAgreement signed Oconto, WIMISO Jun 2020target 2026
Solar project J1746, Columbia County
Solar
150 MWAgreement signed Columbia, WIMISO Jun 2020target 2028
Solar project J1778, Kenosha County
Solar
100 MWAgreement signed Kenosha, WIMISO Jun 2020target 2027
Solar project J1745, Winnebago County
Solar
100 MWAgreement signed Winnebago, WIMISO Jun 2020target 2028
Solar project J1657, St. Croix County
Solar
100 MWIn study St. Croix, WIMISO Jun 2020target 2025
Solar project J1706, Green County
Solar
100 MWAgreement signed Green, WIMISO Jun 2020target 2028
Onshore wind project J1508, Marathon County
Onshore wind
98.9 MWAgreement signed Marathon, WIMISO Jun 2020target 2026
Solar project J1732, Columbia County
Solar
98.4 MWAgreement signed Columbia, WIMISO Jun 2020target 2025
Solar project J1793, Sheboygan County
Solar
75.0 MWAgreement signed Sheboygan, WIMISO Jun 2020target 2028
Solar project J1824, Columbia County
Solar
73.8 MWAgreement signed Columbia, WIMISO Jun 2020target 2025

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)