United States β€Ί Grid β€Ί Interconnection queues β€Ί Washington

OCTARY USA Β· INTERCONNECTION QUEUES

Interconnection queue in Washington (2025 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown176,539 MW
Active in queue6,539 MW17 requests
Agreement signed0.0 MW0 requests
Withdrawn91,114 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

17 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Solar + storage project G1087, Yakima County
Solar + storage
1,000 MWIn study Yakima, WAWest Dec 2025target 2031
Solar + storage project G1082, Yakima County
Solar + storage
800 MWIn study Yakima, WAWest Jul 2025target 2032
Solar + storage project G1080, Yakima County
Solar + storage
800 MWIn study Yakima, WAWest Jul 2025target 2032
Solar + storage project G1081, Yakima County
Solar + storage
800 MWIn study Yakima, WAWest Jul 2025target 2032
Solar + storage project G1083, Yakima County
Solar + storage
800 MWIn study Yakima, WAWest Jul 2025target 2032
Solar + storage project CS25-09, Adams County
Solar + storage
375 MWIn study Adams, WAWest Apr 2025target 2030
Solar + storage project G1086, Columbia County
Solar + storage
359 MWIn study Columbia, WAWest Aug 2025target 2029
Onshore wind project CS25-11, Garfield County
Onshore wind
300 MWIn study Garfield, WAWest Apr 2025target 2029
Battery storage project CS25-08, Spokane County
Battery storage
250 MWIn study Spokane, WAWest Apr 2025target 2029
Onshore wind project CS25-15, Spokane County
Onshore wind
200 MWIn study Spokane, WAWest Apr 2025target 2030
Onshore wind project CS25-17, Spokane County
Onshore wind
200 MWIn study Spokane, WAWest Apr 2025target 2030
Onshore wind project T2-027, Cowlitz County
Onshore wind
199 MWIn study Cowlitz, WAWest Sep 2025target 2027
Onshore wind project CS25-07, Whitman County
Onshore wind
199 MWIn study Whitman, WAWest Apr 2025target 2029
Battery storage project CS25-03, Spokane County
Battery storage
100 MWIn study Spokane, WAWest Apr 2025target 2030
Onshore wind project T2-022, Walla Walla County
Onshore wind
100 MWIn study Walla Walla, WAWest Sep 2025target 2026
Battery storage project G1076, Yakima County
Battery storage
46.5 MWIn study Yakima, WAWest Mar 2025target 2027
Battery storage project G1079, Franklin County
Battery storage
10.0 MWIn study Franklin, WAWest Jul 2025target 2027

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)