Solar + storage project G0670, Benton County Solar + storage |
1,000 MW | In study |
Benton, WA | West |
Feb 2021 | target 2025 |
Solar + storage project G0688, Benton County Solar + storage |
1,000 MW | In study |
Benton, WA | West |
Aug 2021 | target 2025 |
Solar + storage project G0684, Benton County Solar + storage |
705 MW | In study |
Benton, WA | West |
Jul 2021 | target 2024 |
Other project 110, Garfield County Other |
560 MW | In study |
Garfield, WA | West |
Jan 2021 | target 2025 |
Solar + storage project G0668, Grant County Solar + storage |
500 MW | In study |
Grant, WA | West |
Jan 2021 | target 2025 |
Wind + storage project TCS-14, Garfield County Wind + storage |
375 MW | Under construction |
Garfield, WA | West |
Jan 2021 | target 2027 |
Battery storage project 99, King County Battery storage |
250 MW | Paused / redesign |
King, WA | West |
Apr 2021 | target 2028 |
Solar + storage project G0676, Klickitat County Solar + storage |
250 MW | In study |
Klickitat, WA | West |
Mar 2021 | target 2024 |
Onshore wind project G0683, Benton County Onshore wind |
233 MW | In study |
Benton, WA | West |
Jul 2021 | target 2026 |
Gas project 113, Lewis County Gas |
219 MW | Paused / redesign |
Lewis, WA | West |
Jul 2021 | target 2029 |
Gas project 114, Kitsap County Gas |
215 MW | Paused / redesign |
Kitsap, WA | West |
Jul 2021 | target 2029 |
Battery storage project 101, King County Battery storage |
200 MW | Paused / redesign |
King, WA | West |
Apr 2021 | target 2028 |
Onshore wind project G0671, Walla Walla County Onshore wind |
200 MW | In study |
Walla Walla, WA | West |
Feb 2021 | target 2025 |
Battery storage project 109, Kitsap County Battery storage |
200 MW | Paused / redesign |
Kitsap, WA | West |
May 2021 | target 2029 |
Battery storage project 98, Pierce County Battery storage |
200 MW | Agreement signed |
Pierce, WA | West |
Mar 2021 | target 2026 |
Battery storage project 100, Pierce County Battery storage |
200 MW | Paused / redesign |
Pierce, WA | West |
Apr 2021 | target 2028 |
Battery storage project 103, Skagit County Battery storage |
200 MW | Paused / redesign |
Skagit, WA | West |
Apr 2021 | target 2028 |
Solar + storage project C1-37, Kittitas County Solar + storage Β· Badger Gap PV I, LLC |
199 MW | Paused / redesign |
Kittitas, WA | West |
May 2021 | target 2024 |
Battery storage project 129, Kitsap County Battery storage |
170 MW | Agreement signed |
Kitsap, WA | West |
Dec 2021 | target 2029 |
Solar + storage project G0716, Benton County Solar + storage |
150 MW | In study |
Benton, WA | West |
Dec 2021 | target 2025 |
Solar + storage project C1-40, Yakima County Solar + storage Β· CG Yakima County Solar I LLC |
150 MW | In study |
Yakima, WA | West |
May 2021 | target 2025 |
Battery storage project 102, Thurston County Battery storage |
150 MW | Paused / redesign |
Thurston, WA | West |
Apr 2021 | target 2028 |
Solar + storage project G0691, Benton County Solar + storage |
130 MW | In study |
Benton, WA | West |
Sep 2021 | target 2023 |
Solar project G0686, Benton County Solar |
128 MW | In study |
Benton, WA | West |
Aug 2021 | target 2028 |
Battery storage project 112, Thurston County Battery storage |
127 MW | Agreement signed |
Thurston, WA | West |
Jun 2021 | target 2029 |
Battery storage project 121, King County Battery storage |
125 MW | Paused / redesign |
King, WA | West |
Aug 2021 | target 2030 |
Solar + storage project C1-27, Benton County Solar + storage Β· Solway Solar Energy LLC |
100 MW | Paused / redesign |
Benton, WA | West |
May 2021 | target 2023 |
Battery storage project 124, Pierce County Battery storage |
85.0 MW | Paused / redesign |
Pierce, WA | West |
Aug 2021 | target 2029 |
Battery storage project G0717, Klickitat County Battery storage |
75.0 MW | In study |
Klickitat, WA | West |
Dec 2021 | target 2024 |
Onshore wind project G0721, Benton County Onshore wind |
13.6 MW | In study |
Benton, WA | West |
Dec 2021 | target 2024 |
Solar project G0689, Franklin County Solar |
13.3 MW | In study |
Franklin, WA | West |
Sep 2021 | target 2023 |
Solar + storage project 120, Spokane County Solar + storage |
1.0 MW | In study |
Spokane, WA | West |
Aug 2021 | target 2022 |