United States β€Ί Grid β€Ί Interconnection queues β€Ί Washington

OCTARY USA Β· INTERCONNECTION QUEUES

Interconnection queue in Washington (2021 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown328,123 MW
Active in queue8,123 MW32 requests
Agreement signed497 MW3 requests
Withdrawn346,840 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

32 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Solar + storage project G0670, Benton County
Solar + storage
1,000 MWIn study Benton, WAWest Feb 2021target 2025
Solar + storage project G0688, Benton County
Solar + storage
1,000 MWIn study Benton, WAWest Aug 2021target 2025
Solar + storage project G0684, Benton County
Solar + storage
705 MWIn study Benton, WAWest Jul 2021target 2024
Other project 110, Garfield County
Other
560 MWIn study Garfield, WAWest Jan 2021target 2025
Solar + storage project G0668, Grant County
Solar + storage
500 MWIn study Grant, WAWest Jan 2021target 2025
Wind + storage project TCS-14, Garfield County
Wind + storage
375 MWUnder construction Garfield, WAWest Jan 2021target 2027
Battery storage project 99, King County
Battery storage
250 MWPaused / redesign King, WAWest Apr 2021target 2028
Solar + storage project G0676, Klickitat County
Solar + storage
250 MWIn study Klickitat, WAWest Mar 2021target 2024
Onshore wind project G0683, Benton County
Onshore wind
233 MWIn study Benton, WAWest Jul 2021target 2026
Gas project 113, Lewis County
Gas
219 MWPaused / redesign Lewis, WAWest Jul 2021target 2029
Gas project 114, Kitsap County
Gas
215 MWPaused / redesign Kitsap, WAWest Jul 2021target 2029
Battery storage project 101, King County
Battery storage
200 MWPaused / redesign King, WAWest Apr 2021target 2028
Onshore wind project G0671, Walla Walla County
Onshore wind
200 MWIn study Walla Walla, WAWest Feb 2021target 2025
Battery storage project 109, Kitsap County
Battery storage
200 MWPaused / redesign Kitsap, WAWest May 2021target 2029
Battery storage project 98, Pierce County
Battery storage
200 MWAgreement signed Pierce, WAWest Mar 2021target 2026
Battery storage project 100, Pierce County
Battery storage
200 MWPaused / redesign Pierce, WAWest Apr 2021target 2028
Battery storage project 103, Skagit County
Battery storage
200 MWPaused / redesign Skagit, WAWest Apr 2021target 2028
Solar + storage project C1-37, Kittitas County
Solar + storage Β· Badger Gap PV I, LLC
199 MWPaused / redesign Kittitas, WAWest May 2021target 2024
Battery storage project 129, Kitsap County
Battery storage
170 MWAgreement signed Kitsap, WAWest Dec 2021target 2029
Solar + storage project G0716, Benton County
Solar + storage
150 MWIn study Benton, WAWest Dec 2021target 2025
Solar + storage project C1-40, Yakima County
Solar + storage Β· CG Yakima County Solar I LLC
150 MWIn study Yakima, WAWest May 2021target 2025
Battery storage project 102, Thurston County
Battery storage
150 MWPaused / redesign Thurston, WAWest Apr 2021target 2028
Solar + storage project G0691, Benton County
Solar + storage
130 MWIn study Benton, WAWest Sep 2021target 2023
Solar project G0686, Benton County
Solar
128 MWIn study Benton, WAWest Aug 2021target 2028
Battery storage project 112, Thurston County
Battery storage
127 MWAgreement signed Thurston, WAWest Jun 2021target 2029
Battery storage project 121, King County
Battery storage
125 MWPaused / redesign King, WAWest Aug 2021target 2030
Solar + storage project C1-27, Benton County
Solar + storage Β· Solway Solar Energy LLC
100 MWPaused / redesign Benton, WAWest May 2021target 2023
Battery storage project 124, Pierce County
Battery storage
85.0 MWPaused / redesign Pierce, WAWest Aug 2021target 2029
Battery storage project G0717, Klickitat County
Battery storage
75.0 MWIn study Klickitat, WAWest Dec 2021target 2024
Onshore wind project G0721, Benton County
Onshore wind
13.6 MWIn study Benton, WAWest Dec 2021target 2024
Solar project G0689, Franklin County
Solar
13.3 MWIn study Franklin, WAWest Sep 2021target 2023
Solar + storage project 120, Spokane County
Solar + storage
1.0 MWIn study Spokane, WAWest Aug 2021target 2022

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)