United States β€Ί Grid β€Ί Interconnection queues β€Ί Washington

OCTARY USA Β· INTERCONNECTION QUEUES

Withdrawn queue requests in Washington (2024 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown233,050 MW
Active in queue2,717 MW17 requests
Agreement signed344 MW5 requests
Withdrawn233,050 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

23 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Battery storage project 147, Skagit County
Battery storage
200 MWWithdrawn / abandoned Skagit, WAWest Apr 2024target 2027
Solar + storage project PIS064, Yakima County
Solar + storage Β· PacifiCorp
200 MWWithdrawn / abandoned Yakima, WAWest Jun 2024target 2028
Solar + storage project PIS063, Kittitas County
Solar + storage Β· PacifiCorp
200 MWWithdrawn / abandoned Kittitas, WAWest Jun 2024target 2028
Solar + storage project C4-076, Yakima County
Solar + storage Β· PacifiCorp
200 MWWithdrawn / abandoned Yakima, WAWest May 2024target 2028
Solar + storage project C4-075, Kittitas County
Solar + storage Β· PacifiCorp
200 MWWithdrawn / abandoned Kittitas, WAWest May 2024target 2028
Solar + storage project C4-013, Franklin County
Solar + storage
199 MWWithdrawn / abandoned Franklin, WAWest May 2024target 2027
Solar + storage project C4-038, Walla Walla County
Solar + storage
199 MWWithdrawn / abandoned Walla Walla, WAWest May 2024target 2028
Solar + storage project CS24-08, Franklin County
Solar + storage
199 MWWithdrawn / abandoned Franklin, WAWest Apr 2024target 2028
Onshore wind project C4-110, Cowlitz County
Onshore wind
199 MWWithdrawn / abandoned Cowlitz, WAWest May 2024target 2027
Battery storage project C4-045, Walla Walla County
Battery storage
199 MWWithdrawn / abandoned Walla Walla, WAWest May 2024target 2028
Wind + storage project 142, Skagit County
Wind + storage
150 MWWithdrawn / abandoned Skagit, WAWest Mar 2024target 2029
Battery storage project CS24-03, Adams County
Battery storage
150 MWWithdrawn / abandoned Adams, WAWest Apr 2024target 2031
Battery storage project 151, Pierce County
Battery storage
100 MWWithdrawn / abandoned Pierce, WAWest Apr 2024target 2027
Battery storage project 144, Skagit County
Battery storage
100 MWWithdrawn / abandoned Skagit, WAWest Apr 2024target 2027
Battery storage project CS24-04, Spokane County
Battery storage
100 MWWithdrawn / abandoned Spokane, WAWest Apr 2024target 2028
Battery storage project 143, King County
Battery storage
100 MWWithdrawn / abandoned King, WAWest Apr 2024target 2027
Solar project CS24-13, Whitman County
Solar
95.0 MWWithdrawn / abandoned Whitman, WAWest Apr 2024target 2027
Solar + storage project CS24-10, Spokane County
Solar + storage
80.0 MWWithdrawn / abandoned Spokane, WAWest Apr 2024target 2028
Solar project CS24-11, Whitman County
Solar
70.0 MWWithdrawn / abandoned Whitman, WAWest Apr 2024target 2027
Solar project G1073, Benton County
Solar
60.0 MWWithdrawn / abandoned Benton, WAWest Sep 2024target 2026
Solar project CS24-12, Whitman County
Solar
40.0 MWWithdrawn / abandoned Whitman, WAWest Apr 2024target 2027
Solar project CS24-09, Adams County
Solar
9.5 MWWithdrawn / abandoned Adams, WAWest Apr 2024target 2027
Solar project G1067, Adams County
Solar
1.0 MWWithdrawn / abandoned Adams, WAWest May 2024target 2024

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)