Solar project CS24-09, Adams County

Solar project CS24-09, Adams County is a 9.5 MW solar request withdrawn in the West interconnection queue, in Adams County, Washington, connecting to Avista Utilities.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2024 (completed)
  2. Withdrawn / abandonedOct 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
CS24-09
Grid region
West (non-ISO utilities)
Utility / transmission owner
Avista Utilities
Connection point (POI)
Othello 13kV
Location
Adams County, Washington
Technology
Solar: 9.5 MW
Total requested
9.5 MW
Service type
Network resource (NRIS)
Study phase
Request Status: Withdrawn; Facilities Study: Complete; Phase One Cluster Study: Complete; Phase One Re-Study: N/A; Phase
Queue status
Withdrawn
Entered queue
29 April 2024
Proposed online date
March 2027
Withdrawn
October 2025

Location

Marker shows the centre of Adams County; the queue data does not give exact sites.

Power plants in Washington Β· Transmission lines in Washington

Other requests in Adams County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem