Requests shown373,574 MW
Active in queue0.0 MW0 requests
Agreement signed0.0 MW0 requests
Withdrawn373,574 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

37 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Battery storage project 1167, Box Elder County
Battery storage
650 MWWithdrawn / abandoned Box Elder, UTWest Sep 2019target 2021
Battery storage project 1166, Box Elder County
Battery storage
400 MWWithdrawn / abandoned Box Elder, UTWest Sep 2019target 2021
Solar + storage project 1100, Emery County
Solar + storage
250 MWWithdrawn / abandoned Emery, UTWest Jan 2019target 2021
Battery storage project 1175, Salt Lake County
Battery storage
200 MWWithdrawn / abandoned Salt Lake, UTWest Oct 2019target 2024
Battery storage project 1177, Utah County
Battery storage
200 MWWithdrawn / abandoned Utah, UTWest Oct 2019target 2023
Battery storage project 1181, Juab County
Battery storage
200 MWWithdrawn / abandoned Juab, UTWest Oct 2019target 2023
Battery storage project 1180, Juab County
Battery storage
200 MWWithdrawn / abandoned Juab, UTWest Oct 2019target 2023
Battery storage project 1179, Salt Lake County
Battery storage
200 MWWithdrawn / abandoned Salt Lake, UTWest Oct 2019target 2023
Battery storage project 1178, Salt Lake County
Battery storage
200 MWWithdrawn / abandoned Salt Lake, UTWest Oct 2019target 2023
Battery storage project 1176, Salt Lake County
Battery storage
200 MWWithdrawn / abandoned Salt Lake, UTWest Oct 2019target 2023
Solar project 1130, Iron County
Solar
120 MWWithdrawn / abandoned Iron, UTWest Apr 2019target 2022
Battery storage project 1117, Salt Lake County
Battery storage
90.0 MWWithdrawn / abandoned Salt Lake, UTWest Feb 2019target 2021
Solar project 1129, Millard County
Solar
78.0 MWWithdrawn / abandoned Millard, UTWest Apr 2019target 2022
Solar + storage project 1101, Millard County
Solar + storage
75.0 MWWithdrawn / abandoned Millard, UTWest Jan 2019target 2021
Solar + storage project 1102, San Juan County
Solar + storage
75.0 MWWithdrawn / abandoned San Juan, UTWest Jan 2019target 2021
Solar project 1119, San Juan County
Solar
66.0 MWWithdrawn / abandoned San Juan, UTWest Mar 2019target 2021
Solar + storage project 1111, Emery County
Solar + storage
60.0 MWWithdrawn / abandoned Emery, UTWest Feb 2019target 2021
Solar + storage project TCS-27, Salt Lake County
Solar + storage Β· Inland Port Renewable Energy, LLC
60.0 MWWithdrawn / abandoned Salt Lake, UTWest Feb 2019target 2025
Solar + storage project 1112, Emery County
Solar + storage
60.0 MWWithdrawn / abandoned Emery, UTWest Feb 2019target 2021
Solar project 1170, San Juan County
Solar
35.0 MWWithdrawn / abandoned San Juan, UTWest Oct 2019target 2023
Geothermal project 1159, Beaver County
Geothermal
31.1 MWWithdrawn / abandoned Beaver, UTWest Sep 2019target 2020
Geothermal project TCS-41, Beaver County
Geothermal Β· Intermountain Renewable Power, LLC
31.1 MWWithdrawn / abandoned Beaver, UTWest Sep 2019target 2026
Solar project 1103, Iron County
Solar
30.0 MWWithdrawn / abandoned Iron, UTWest Jan 2019target 2022
Solar project TCS-25, Iron County
Solar
30.0 MWWithdrawn / abandoned Iron, UTWest Jan 2019target 2022
Solar project 1140, Salt Lake County
Solar
5.5 MWWithdrawn / abandoned Salt Lake, UTWest May 2019target 2020
Solar project 1146, Box Elder County
Solar
3.0 MWWithdrawn / abandoned Box Elder, UTWest Jun 2019target 2021
Solar project 1157, Tremonton County
Solar
3.0 MWWithdrawn / abandoned Tremonton, UTWest Aug 2019target 2021
Solar project TCS-32, Box Elder County
Solar
3.0 MWWithdrawn / abandoned Box Elder, UTWest Apr 2019target 2021
Solar project TCS-29, Box Elder County
Solar
3.0 MWWithdrawn / abandoned Box Elder, UTWest Mar 2019target 2021
Solar project 1123, Box Elder County
Solar
3.0 MWWithdrawn / abandoned Box Elder, UTWest Mar 2019target 2021
Solar project TCS-36, Box Elder County
Solar
3.0 MWWithdrawn / abandoned Box Elder, UTWest Jun 2019target 2021
Solar project 1132, Box Elder County
Solar
3.0 MWWithdrawn / abandoned Box Elder, UTWest Apr 2019target 2021
Solar project 1113, Emery County
Solar
2.8 MWWithdrawn / abandoned Emery, UTWest Feb 2019target 2019
Solar project TCS-35, Box Elder County
Solar
1.0 MWWithdrawn / abandoned Box Elder, UTWest Jun 2019target 2021
Solar project 1145, Box Elder County
Solar
1.0 MWWithdrawn / abandoned Box Elder, UTWest Jun 2019target 2021
Solar project 1152, Utah County
Solar
0.7 MWWithdrawn / abandoned Utah, UTWest Jul 2019
Solar project 1187, Grand County
Solar
0.3 MWWithdrawn / abandoned Grand, UTWest Oct 2019target 2020

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)