πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Utah

OCTARY USA Β· INTERCONNECTION QUEUES

Completed queue projects in Utah (2016 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown121,003 MW
Active in queue4,313 MW14 requests
Agreement signed1,463 MW8 requests
Withdrawn324,651 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

12 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Solar + storage project 778, Emery County
Solar + storage Β· Hornshadow Solar 2, LLC
200 MWOperating Emery, UTWest Jul 2016target 2024
Solar project 763, Iron County
Solar Β· Appaloosa Solar I, LLC
200 MWOperating Iron, UTWest Jun 2016target 2023
Solar project 737, Washington County
Solar Β· Cove Mountain Solar 2, LLC
122 MWOperating Washington, UTWest Apr 2016target 2020
Solar project 777, Emery County
Solar Β· Hornshadow Solar, LLC
100 MWOperating Emery, UTWest Jul 2016target 2025
Solar project 766, Emery County
Solar Β· Hunter Solar, LLC
100 MWOperating Emery, UTWest Jun 2016target 2020
Solar project 764, Carbon County
Solar Β· Graphite Solar I, LLC
80.0 MWOperating Carbon, UTWest Jun 2016target 2021
Solar project 753, Box Elder County
Solar Β· Rocket Solar, LLC
80.0 MWOperating Box Elder, UTWest May 2016target 2023
Solar project 804, Juab County
Solar Β· Clover Creek Solar, LLC
80.0 MWOperating Juab, UTWest Sep 2016target 2021
Solar project 752, Emery County
Solar Β· Castle Solar, LLC
40.0 MWOperating Emery, UTWest May 2016target 2023
Hydro project 732, Cache County
Hydro Β· Richmond Irrigation Company
0.3 MWOperating Cache, UTWest Mar 2016target 2017
Battery storage project 725, Weber County
Battery storage Β· SolarCity Corporation
0.3 MWOperating Weber, UTWest Jan 2016target 2017
Gas project 742, Salt Lake County
Gas Β· The Church of Jesus Christ of Latter-Day Saints
0.2 MWOperating Salt Lake, UTWest May 2016target 2017

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)