Solar project 804, Juab County

Solar project 804, Juab County is a 80.0 MW solar request built and operating in the West interconnection queue, in Juab County, Utah, connecting to PacifiCorp.

Queue statusOperating
  1. PlanningQueued Sep 2016 (completed)
  2. ConsentedMay 2019 (completed)
  3. Construction (completed)
  4. OperatingTarget Oct 2021 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
804
Grid region
West (non-ISO utilities)
Utility / transmission owner
PacifiCorp
Developer
Clover Creek Solar, LLC
Connection point (POI)
Mona substation
Location
Juab County, Utah
Technology
Solar: 80.0 MW
Total requested
80.0 MW
Service type
Network resource (NRIS)
Study phase
IA executed 5/29/19
Queue status
Operational
Entered queue
26 September 2016
Agreement signed
29 May 2019
Proposed online date
October 2021

Location

Marker shows the centre of Juab County; the queue data does not give exact sites.

Power plants in Utah · Transmission lines in Utah

Other requests in Juab County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem