United States β€Ί Grid β€Ί Interconnection queues β€Ί Texas

OCTARY USA Β· INTERCONNECTION QUEUES

Withdrawn queue requests in Texas (2013 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown62,242 MW
Active in queue966 MW5 requests
Agreement signed162 MW1 requests
Withdrawn62,242 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

6 requests
ProjectCapacityStatusLocationRegionQueuedOnline
FGE Texas 1 Gas
Gas Β· FGE Power
743 MWWithdrawn / abandoned Mitchell, TXERCOT Apr 2013target 2021
Gas project GEN-2013-031, Randall County
Gas
370 MWWithdrawn / abandoned Randall, TXSPP Sep 2013target 2016
Hale Community W 1
Onshore wind Β· Nextera
322 MWWithdrawn / abandoned Hale, TXERCOT Nov 2013target 2020
Easter Wind
Onshore wind Β· TriGlobal
308 MWWithdrawn / abandoned Castro, TXERCOT Dec 2013target 2021
Onshore wind project GEN-2013-030, Ochiltree County
Onshore wind
300 MWWithdrawn / abandoned Ochiltree, TXSPP Sep 20132020
Onshore wind project GEN-2013-017, Crosby County
Onshore wind
200 MWWithdrawn / abandoned Crosby, TXSPP Mar 2013target 2014

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)