United States β€Ί Grid β€Ί Interconnection queues β€Ί Tennessee

OCTARY USA Β· INTERCONNECTION QUEUES

Interconnection queue in Tennessee (2023 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown5720 MW
Active in queue720 MW5 requests
Agreement signed150 MW1 requests
Withdrawn356,982 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

5 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Gas project 588, Shelby County
Gas
238 MWIn study Shelby, TNSoutheast Nov 2023target 2024
Battery storage project 587, Hawkins County
Battery storage
225 MWIn study Hawkins, TNSoutheast Oct 2023target 2029
Solar + storage project 538, Henderson County
Solar + storage
150 MWAgreement signed Henderson, TNSoutheast Mar 2023target 2029
Battery storage project 547, Roane County
Battery storage
100 MWIn study Roane, TNSoutheast Apr 2023target 2026
Hydro project 590, Marion County
Hydro
7.0 MWIn study Marion, TNSoutheast Nov 2023target 2028

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)