United States β€Ί Grid β€Ί Interconnection queues β€Ί Pennsylvania

OCTARY USA Β· INTERCONNECTION QUEUES

Completed queue projects in Pennsylvania (2014 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown173,629 MW
Active in queue0.0 MW0 requests
Agreement signed0.0 MW0 requests
Withdrawn265,501 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

17 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Freedom Generation Plant
Gas
1,050 MWOperating Luzerne, PAPJM Mar 20142018
CPV Fairview Energy Center
Gas
1,050 MWOperating Cambria, PAPJM Oct 20142019
Hickory Run Energy Station
Gas
1,000 MWOperating Lawrence, PAPJM Aug 20142019
Delta York
Gas
120 MWOperating York, PAPJM Jul 20142018
Lackawanna Thermal Generating Station
Gas
113 MWOperating Lackawanna, PAPJM Oct 20142019
Ford Mill
Gas
74.0 MWOperating Bucks, PAPJM Oct 20142016
Liberty/Asylum Township Plant
Gas
57.5 MWOperating Bradford, PAPJM Oct 20142016
Patriot Generating Station
Gas
57.0 MWOperating Lycoming, PAPJM Nov 20142016
Ontelaunee Power Generating Plant
Gas
34.1 MWOperating Berks, PAPJM Aug 20142017
Other project J374, Bucks County
Other
30.0 MWOperating Bucks, PAMISO Jul 20142014
Meyersdale Wind Farm & Battery Energy Storage System
Battery storage
18.0 MWOperating Somerset, PAPJM Apr 20142015
AES Warrior Run Energy Storage
Battery storage
11.0 MWOperating Allegheny, PAPJM Oct 20142015
Piney Station (Piney 1-3)
Hydro
5.3 MWOperating Clarion, PAPJM Aug 20142015
Fayette Energy Facility
Gas
5.0 MWOperating Fayette, PAPJM Jun 20142015
Oxbow Creek Generation Plant
Gas
1.6 MWOperating Wyoming, PAPJM Apr 20142019
Mahoning Creek Hydroelectric Plant
Hydro
1.5 MWOperating Clarion, PAPJM Apr 20142014
Roundtop Energy Project
Gas
1.0 MWOperating Susquehanna, PAPJM Apr 20142016

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)