United States › Grid › Interconnection queues › Pennsylvania
GAS · PJMRoundtop Energy Project
Roundtop Energy Project is a 1.0 MW gas request built and operating in the PJM interconnection queue, in Susquehanna County, Pennsylvania, connecting to PENELEC.
Request details
- Queue ID
- Z2-103
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- PENELEC
- Connection point (POI)
- North Meshoppen 34.5kV III
- Location
- Susquehanna County, Pennsylvania
- Technology
- Gas: 1.0 MW
- Total requested
- 1.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- Available studies: Feasibility Study, System Impact Study; Interim/Interconnection Service Agreement: Document Posted
- Queue status
- Operational
- Entered queue
- 30 April 2014
- Proposed online date
- December 2016
- Came online
- January 2016
Location
Marker shows the centre of Susquehanna County; the queue data does not give exact sites.
Power plants in Pennsylvania · Transmission lines in Pennsylvania
Other requests in Susquehanna County
- Solar project AH2-189, Susquehanna CountySolar · 12.0 MW · in study
- Other project AH2-001, Susquehanna CountyOther · 3.6 MW · in study
- Roundtop Energy ProjectGas · 3.5 MW · built
- Roundtop Energy ProjectsGas · 1.5 MW · built
- Solar + storage project AH1-419, Susquehanna CountySolar + storage · 20.0 MW · withdrawn
- Thompson 34.5kVGas · 19.9 MW · withdrawn
- Gas project AB1-083, Susquehanna CountyGas · 19.9 MW · withdrawn
- Gas project AA2-112, Susquehanna CountyGas · 19.9 MW · withdrawn
- Gas project AB1-084, Susquehanna CountyGas · 19.9 MW · withdrawn
- Solar project AG2-294, Susquehanna CountySolar · 18.0 MW · withdrawn
- Solar project AG2-293, Susquehanna CountySolar · 18.0 MW · withdrawn
- Solar project AG2-291, Susquehanna CountySolar · 16.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem