GAS · PJMPatriot Generating Station
Patriot Generating Station is a 57.0 MW gas request built and operating in the PJM interconnection queue, in Lycoming County, Pennsylvania, connecting to PPL.
Request details
- Queue ID
- AA2-008
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- PPL
- Connection point (POI)
- Saegers 230 kV
- Location
- Lycoming County, Pennsylvania
- Technology
- Gas: 57.0 MW
- Total requested
- 57.0 MW
- Service type
- Energy only (ERIS)
- Study phase
- Available studies: Feasibility Study, System Impact Study; Interim/Interconnection Service Agreement: Document Posted
- Queue status
- Operational
- Entered queue
- 6 November 2014
- Proposed online date
- September 2016
- Came online
- September 2016
Location
Marker shows the centre of Lycoming County; the queue data does not give exact sites.
Power plants in Pennsylvania · Transmission lines in Pennsylvania
Other requests in Lycoming County
- Solar project AI2-195, Lycoming CountySolar · 69.9 MW · in study
- Solar project AI2-196, Lycoming CountySolar · 51.5 MW · in study
- Solar + storage project AI2-434, Lycoming CountySolar + storage · 20.0 MW · in study
- Solar + storage project AI1-129, Lycoming CountySolar + storage · 4.5 MW · in study
- Patriot Generating StationGas · 850 MW · built
- Laurel HillOnshore wind · 70.0 MW · built
- Solar project AF1-216, Lycoming CountySolar · 143 MW · withdrawn
- Solar + storage project AG2-417, Lycoming CountySolar + storage · 100 MW · withdrawn
- Solar project AF2-145, Lycoming CountySolar · 51.0 MW · withdrawn
- Solar project AG2-398, Lycoming CountySolar · 10.0 MW · withdrawn
- Gas project G49, Lycoming CountyGas · 10.0 MW · withdrawn
- Solar project AG2-156, Lycoming CountySolar · 5.1 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem