🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Pennsylvania

ONSHORE WIND · PJM

Laurel Hill

Laurel Hill is a 70.0 MW onshore wind request built and operating in the PJM interconnection queue, in Lycoming County, Pennsylvania, connecting to PENELEC.

Queue statusOperating
  1. PlanningQueued Feb 2003 (completed)
  2. ConsentedAug 2005 (completed)
  3. Construction (completed)
  4. OperatingSep 2012 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
K02
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
PENELEC
Connection point (POI)
East Towanda-Moshannon 230kV
Location
Lycoming County, Pennsylvania
Technology
Wind: 70.0 MW
Total requested
70.0 MW
Service type
Energy only (ERIS)
Study phase
Available studies: Feasibility Study, System Impact Study, Facilities Study; Interim/Interconnection Service Agreement:
Queue status
Operational
Entered queue
25 February 2003
Agreement signed
31 August 2005
Proposed online date
October 2012
Came online
September 2012

Location

Marker shows the centre of Lycoming County; the queue data does not give exact sites.

Power plants in Pennsylvania · Transmission lines in Pennsylvania

Other requests in Lycoming County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem