United States β€Ί Grid β€Ί Interconnection queues β€Ί Oklahoma

OCTARY USA Β· INTERCONNECTION QUEUES

Withdrawn queue requests in Oklahoma (2014 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown111,501 MW
Active in queue0.0 MW0 requests
Agreement signed0.0 MW0 requests
Withdrawn111,501 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

11 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Onshore wind project GEN-2014-058, Blaine County
Onshore wind
300 MWWithdrawn / abandoned Blaine, OKSPP Sep 2014target 2016
Onshore wind project GEN-2014-062, Kiowa County
Onshore wind
200 MWWithdrawn / abandoned Kiowa, OKSPP Sep 2014target 2016
Onshore wind project GEN-2014-052, Beaver County
Onshore wind
200 MWWithdrawn / abandoned Beaver, OKSPP Sep 2014target 2016
Onshore wind project GEN-2014-037, Texas County
Onshore wind
200 MWWithdrawn / abandoned Texas, OKSPP Sep 2014target 2017
Onshore wind project GEN-2014-061, Blaine County
Onshore wind
161 MWWithdrawn / abandoned Blaine, OKSPP Sep 2014target 2016
Onshore wind project GEN-2014-026, Beaver County
Onshore wind
150 MWWithdrawn / abandoned Beaver, OKSPP Sep 2014target 2016
Onshore wind project GEN-2014-014, Pontotoc County
Onshore wind
150 MWWithdrawn / abandoned Pontotoc, OKSPP Jun 2014target 2017
Gas project GEN-2014-027, Okfuskee County
Gas
60.0 MWWithdrawn / abandoned Okfuskee, OKSPP Sep 2014target 2016
Solar project GEN-2014-036, Harmon County
Solar
50.0 MWWithdrawn / abandoned Harmon, OKSPP Sep 2014target 2016
Onshore wind project GEN-2014-003, Blaine County
Onshore wind
15.8 MWWithdrawn / abandoned Blaine, OKSPP Feb 20142014
Onshore wind project GEN-2014-022, Kay County
Onshore wind
15.0 MWWithdrawn / abandoned Kay, OKSPP Sep 2014target 2015

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)