United States β€Ί Grid β€Ί Interconnection queues β€Ί Ohio

OCTARY USA Β· INTERCONNECTION QUEUES

Queue requests in study in Ohio (2018 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown7534 MW
Active in queue1,184 MW11 requests
Agreement signed650 MW4 requests
Withdrawn205,570 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

7 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Fountain Point Solar
Solar Β· Fountain Point Solar Energy LLC
207 MWIn study Union, OHPJM Aug 2018target 2021
Strawhat Solar Energy Center
Solar
110 MWPaused / redesign Hardin, OHPJM Aug 2018target 2026
Hardin Energy Center β€šΓ„Γ¬ Storage I
Battery storage
50.0 MWPaused / redesign Hardin, OHPJM Mar 2018target 2025
Cadence Energy Storage
Battery storage
50.0 MWPaused / redesign Union, OHPJM Mar 2018target 2026
Recreation Solar
Solar
49.5 MWPaused / redesign Guernsey, OHPJM Sep 2018target 2025
Vinton Energy Storage
Battery storage
42.0 MWPaused / redesign Vinton, OHPJM Aug 2018target 2026
Blue Creek Wind Farm
Solar
26.0 MWPaused / redesign Van Wert, OHPJM Sep 2018target 2024

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)