United States β€Ί Grid β€Ί Interconnection queues β€Ί Ohio

OCTARY USA Β· INTERCONNECTION QUEUES

Queue requests in study in Ohio (2017 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown5405 MW
Active in queue1,127 MW11 requests
Agreement signed723 MW6 requests
Withdrawn525,731 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

5 requests
ProjectCapacityStatusLocationRegionQueuedOnline
South Branch Solar
Solar
205 MWPaused / redesign Hancock, OHPJM Aug 2017target 2025
Circleville Solar Energy
Solar
70.0 MWPaused / redesign Pickaway, OHPJM Feb 2017target 2027
Chestnut Solar
Solar
60.0 MWPaused / redesign Marion, OHPJM Sep 2017target 2026
Steubenville Solar
Solar
49.5 MWPaused / redesign Jefferson, OHPJM Nov 2017target 2027
Blue Creek Wind Farm
Solar
20.0 MWPaused / redesign Van Wert, OHPJM Feb 2017target 2024

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)