Projects with signed interconnection agreements in North Dakota

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown132,129 MW
Active in queue14.5 GW63 requests
Agreement signed2,129 MW13 requests
Withdrawn28555.0 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

13 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Onshore wind project MPC04000, Oliver County
Onshore wind
300 MWAgreement signed Oliver, NDMISO Apr 2019target 2023
Onshore wind project GEN-2018-067, Williams County
Onshore wind
255 MWAgreement signed Williams, NDSPP Oct 2018target 2028
Onshore wind project MPC03800, Eddy County
Onshore wind
250 MWAgreement signed Eddy, NDMISO Feb 2019target 2027
Onshore wind project GEN-2016-004, Oliver County
Onshore wind
202 MWAgreement signed Oliver, NDSPP Mar 2016target 2027
Solar project MPC03600, Richland County
Solar
170 MWAgreement signed Richland, NDMISO May 2018target 2027
Battery storage project GEN-2023-SR4, Burke County
Battery storage
170 MWAgreement signed Burke, NDSPP Dec 2022target 2026
Onshore wind project MPC03900, Eddy County
Onshore wind
151 MWAgreement signed Eddy, NDMISO Apr 2019target 2027
Solar project GEN-2019-037, Mercer County
Solar
150 MWAgreement signed Mercer, NDSPP May 2019target 2023
Solar project GEN-2020-091, Mckenzie County
Solar
150 MWAgreement signed Mckenzie, NDSPP Apr 2020target 2029
Solar project MPC03700, Richland County
Solar
130 MWAgreement signed Richland, NDMISO May 2018target 2027
Onshore wind project GEN-2017-215, Ward County
Onshore wind
100 MWAgreement signed Ward, NDSPP Nov 2017target 2030
Onshore wind project GEN-2017-214, Ward County
Onshore wind
100 MWAgreement signed Ward, NDSPP Nov 2017target 2030
Gas project GI-1103, Burke County
Gas Β· Blaise Energy
0.8 MWAgreement signed Burke, NDWest Sep 2011target 2011

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)