United States › Grid › Interconnection queues › North Carolina
OCTARY USA · INTERCONNECTION QUEUESWithdrawn queue requests in North Carolina
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Gas project 73054, Davidson County Gas |
1,503 MW | Withdrawn / abandoned |
| Gas project 33170, Person County Gas · Duke Energy Progress, LLC |
1,350 MW | Withdrawn / abandoned |
| Gas project 43466, Person County Gas · Duke Energy Progress, LLC |
1,350 MW | Withdrawn / abandoned |
| Gas project 30612, Wake County Gas · Duke Energy Progress, LLC |
1,350 MW | Withdrawn / abandoned |
| Gas project 43484, Person County Gas · Duke Energy Progress, LLC |
1,350 MW | Withdrawn / abandoned |
| Gas project 72278, Person County Gas · Duke Energy Progress, LLC |
1,350 MW | Withdrawn / abandoned |
| Gas project 43510, Person County Gas · Duke Energy Progress, LLC |
1,350 MW | Withdrawn / abandoned |
| Gas project 43498, Person County Gas · Duke Energy Progress, LLC |
1,350 MW | Withdrawn / abandoned |
| Gas project 113970, Person County Gas · Duke Energy Progress, LLC |
1,350 MW | Withdrawn / abandoned |
| Gas project 17238, Wake County Gas · Duke Energy Progress, LLC |
1,235 MW | Withdrawn / abandoned |
| Gas project 24745, Cumberland County Gas · Duke Energy Progress - Cumberland South - 500 kV |
1,235 MW | Withdrawn / abandoned |
| Gas project 17301, Rowan County Gas |
1,235 MW | Withdrawn / abandoned |
| Gas project 24735, Cumberland County Gas · Duke Energy Progress, LLC |
1,235 MW | Withdrawn / abandoned |
| Solar project AF1-236, Tyrrell County Solar |
1,210 MW | Withdrawn / abandoned |
| Nuclear project 41400, Wake County Nuclear · Duke Energy Progress, LLC |
1,125 MW | Withdrawn / abandoned |
| Gas project 956754, Stokes County Gas |
940 MW | Withdrawn / abandoned |
| Nuclear project 41638, Anson County Nuclear · Masked |
937 MW | Withdrawn / abandoned |
| Gas project 191136, Catawba County Gas |
920 MW | Withdrawn / abandoned |
| Gas project 31964, Wilson County Gas · Duke Energy Progress, LLC |
803 MW | Withdrawn / abandoned |
| Gas project 977563, Rowan County Gas |
703 MW | Withdrawn / abandoned |
| Solar project 66858, Columbus County Solar · Masked |
700 MW | Withdrawn / abandoned |
| Gas project 63826, Rowan County Gas |
692 MW | Withdrawn / abandoned |
| Solar project AC2-093, Northampton County Solar |
675 MW | Withdrawn / abandoned |
| Gas project 31968, Johnston County Gas · Duke Energy Progress, LLC |
602 MW | Withdrawn / abandoned |
| Gas project 33182, Person County Gas · Duke Energy Progress, LLC |
602 MW | Withdrawn / abandoned |
| Gas project 567758, Davidson County Gas |
500 MW | Withdrawn / abandoned |
| Gas project 8599, Buncombe County Gas · Duke Energy Progress, LLC |
470 MW | Withdrawn / abandoned |
| Solar project 66832, Bladen County Solar · Masked |
450 MW | Withdrawn / abandoned |
| Battery storage project 899003, Chatham County Battery storage · Masked |
350 MW | Withdrawn / abandoned |
| Gas project 138414, Gaston County Gas |
348 MW | Withdrawn / abandoned |
| Solar project AE1-133, Alamance County Solar |
300 MW | Withdrawn / abandoned |
| Hales Lake Energy Center Onshore wind |
300 MW | Withdrawn / abandoned |
| Solar + storage project AI1-135, Chowan County Solar + storage |
300 MW | Withdrawn / abandoned |
| Solar project AE1-236, Edgecombe County Solar |
290 MW | Withdrawn / abandoned |
| Solar project 956594, Pamlico County Solar · Masked |
290 MW | Withdrawn / abandoned |
| Gas project 8600, Buncombe County Gas · Duke Energy Progress, LLC |
280 MW | Withdrawn / abandoned |
| Solar project 177046, Duplin County Solar · Masked |
275 MW | Withdrawn / abandoned |
| Solar project 569986, Richmond County Solar · Masked |
275 MW | Withdrawn / abandoned |
| Solar project 170274, Richmond County Solar · Masked |
275 MW | Withdrawn / abandoned |
| Gas project 41118, Chatham County Gas · Duke Energy Progress, LLC |
260 MW | Withdrawn / abandoned |
| Onshore wind project W3-053, Washington County Onshore wind |
260 MW | Withdrawn / abandoned |
| Solar project AG1-439, Edgecombe County Solar · RWE Solar Development, LLC |
250 MW | Withdrawn / abandoned |
| Gas project 40614, Chatham County Gas · Duke Energy Progress, LLC |
224 MW | Withdrawn / abandoned |
| Gas project 41114, Chatham County Gas · Duke Energy Progress, LLC |
224 MW | Withdrawn / abandoned |
| Solar project AF1-073, Washington County Solar |
200 MW | Withdrawn / abandoned |
| Onshore wind project 8603, Carteret County Onshore wind · Masked |
200 MW | Withdrawn / abandoned |
| Solar project 569030, Pender County Solar · Masked |
200 MW | Withdrawn / abandoned |
| Battery storage project 898881, Gaston County Battery storage |
200 MW | Withdrawn / abandoned |
| Battery storage project 899005, Wake County Battery storage · Masked |
200 MW | Withdrawn / abandoned |
| Battery storage project 957073, Guilford County Battery storage |
199 MW | Withdrawn / abandoned |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)