BATTERY STORAGE Β· SOUTHEASTBattery storage project 898881, Gaston County
Battery storage project 898881, Gaston County is a 200 MW battery storage request withdrawn in the Southeast interconnection queue, in Gaston County, North Carolina, connecting to Duke Energy Carolinas.
Queue statusWithdrawn / abandoned
- PlanningQueued Jun 2023 (completed)
- Withdrawn / abandoned (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 898881
- Grid region
- Southeast (non-ISO utilities)
- Utility / transmission owner
- Duke Energy Carolinas
- Connection point (POI)
- Riverbend Steam Station
- Location
- Gaston County, North Carolina
- Technology
- Battery: 200 MW
- Total requested
- 200 MW
- Service type
- NRIS and ERIS
- Study phase
- Withdrawn
- Queue status
- Withdrawn
- Entered queue
- 28 June 2023
Location
Marker shows the centre of Gaston County; the queue data does not give exact sites.
Power plants in North Carolina Β· Transmission lines in North Carolina
Other requests in Gaston County
- Battery storage project 186466, Gaston CountyBattery storage Β· 50.0 MW Β· under construction
- Battery storage project 977301, Gaston CountyBattery storage Β· 250 MW Β· in study
- Battery storage project 956141, Gaston CountyBattery storage Β· 199 MW Β· in study
- Battery storage project 977299, Gaston CountyBattery storage Β· 199 MW Β· in study
- Battery storage project 563648, Gaston CountyBattery storage Β· 115 MW Β· in study
- Gas project 138414, Gaston CountyGas Β· 348 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem